Summary Information | |||||||||||
|
|||||||||||
|
Questions | Answers | References | |||||||
---|---|---|---|---|---|---|---|---|---|
4.5.3 (AW) Line Stations | |||||||||
1
Does the process design ensure the person with responsibility provides adequate resources (financial and human) for the safety and quality performance of this element?
Safety Attribute: Management Responsibility, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:21 AM, QID: 00051929, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
2
Does the process design ensure the person with responsibility provides adequate resources (financial and human) for the safety and quality performance of this element?
Safety Attribute: Management Responsibility, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:22 AM, QID: 00051943, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
3
Is the person with authority clearly identifiable, qualified, and knowledgeable to effectively plan, direct and control resources; change procedures and make key determinations including safety risk acceptance decisions for this element?
Safety Attribute: Management Authority, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:21 AM, QID: 00051930, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
4
Is the person with authority clearly identifiable, qualified, and knowledgeable to effectively plan, direct and control resources; change procedures and make key determinations including safety risk acceptance decisions for this element?
Safety Attribute: Management Authority, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:22 AM, QID: 00051944, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
5
Are there process measures that provide for the monitoring and measuring of safety performance related to this element?
Safety Attribute: Process Measurement, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:21 AM, QID: 00051931, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
6
Are there process measures that provide for the monitoring and measuring of safety performance related to this element?
Safety Attribute: Process Measurement, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:23 AM, QID: 00051945, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
7
Do the line station procedures includes instructions and information that address:
#1 Duties and Responsibilities; #2 Servicing and Ramp Maintenance; #3 Hot and Cold Weather Maintenance; and #4 Contract Services? Safety Attribute: Procedures, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135") AND (LOCATIONS = "AW LINE STATIONS") , Rev. 2 3/14/2017 3:14:42 PM, QID: 00050067, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
8
Do the procedures include the necessary instructions and information to show the following are available to properly maintain and service aircraft:
#1 Competent Personnel; #2 Adequate Facilities; and #3 Equipment? Safety Attribute: Procedures, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135") AND (LOCATIONS = "AW LINE STATIONS") , Rev. 2 3/14/2017 3:14:42 PM, QID: 00050074, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
9
Do the procedures include instructions for operating ground equipment, including the capabilities and limitations of the equipment, and the training and qualification of persons using the equipment?
Safety Attribute: Procedures, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135") AND (LOCATIONS = "AW LINE STATIONS") , Rev. 2 3/14/2017 3:14:43 PM, QID: 00050081, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
10
Do procedures exist in enough detail to meet the regulatory and guidance requirements for this element to produce the intended results?
Safety Attribute: Procedures, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:20 AM, QID: 00051926, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
11
Do procedures exist in enough detail to meet the regulatory and guidance requirements for this element to produce the intended results?
Safety Attribute: Procedures, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:22 AM, QID: 00051940, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
12
Do risk controls exist within this element to mitigate unacceptable levels of risk(s)?
Safety Attribute: Controls, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:20 AM, QID: 00051927, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
13
Do risk controls exist within this element to mitigate unacceptable levels of risk(s)?
Safety Attribute: Controls, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:21 AM, QID: 00051941, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
14
Does the certificate holder have a method to evaluate the impact of changes on related processes (interfaces) for this element?
Safety Attribute: Interfaces, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:21 AM, QID: 00051928, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
15
Does the certificate holder have a method to evaluate the impact of changes on related processes (interfaces) for this element?
Safety Attribute: Interfaces, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:22 AM, QID: 00051942, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
16
Do procedures require individuals be competent in their safety related duties as it relates to safety performance of this element?
Safety Attribute: Safety Ownership, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND (SAFETY PROGRAMS = "SMSVP") , Rev. 1 3/13/2018 11:30:21 AM, QID: 00051932, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
|||||||
17
Do procedures require individuals be competent in their safety related duties as it relates to safety performance of this element?
Safety Attribute: Safety Ownership, Question Type: Output Validation, Scoping Attribute: (FAR PART = "135" OR "145") AND ( NOT (SAFETY PROGRAMS = "SMSVP")) , Rev. 1 3/13/2018 11:30:23 AM, QID: 00051946, Response Details: EP & ED DCTs (Both OP and AW), Status: Released |
|
|
Response Details List EP & ED DCTs (Both OP and AW) (Released, 1.0) | |
1 | Unclear procedure(s) |
2 | Conflicting procedure(s) |
3 | Used workaround(s) |
4 | Skipped process step(s) |
5 | Personnel failed to follow process (procedures, guidance, etc) |
6 | Procedures/guidance not available |
7 | Procedures/guidance not current |
8 | Inconsistent procedure(s) |
9 | Undocumented procedure(s) |
10 | Minor typographical error(s) (i.e. record entries) |
11 | Information missing |
12 | Communication failure(s) |
13 | Personnel failed to perform task |
14 | Process failed to meet desired outcome |
15 | Process oversight failure |
16 | Equipment/tools not available |
17 | Equipment/tools not adequate |
18 | Equipment/tools not calibrated |
19 | Facilities not adequate |
20 | Other |
Response Details List N/A Response Detail (Released, 1.0) | |
1 | Operator not authorized by OpSpecs |
2 | Equipment not equipped/authorized |
3 | Not applicable due to exemption, deviation, or exception |
4 | Not authorized by regulation |
5 | Not authorized by Order |
6 | Not authorized by Notice |
7 | Not authorized/recommended by Advisory Circular |
8 | Not authorized by Policy Letter, Legal Interpretation, or other guidance |
9 | Other |